After no action at site early in the week due to wind and rain, the last 2 days have been really productive.
Looks like the ground floor frame is complete. They had a crane at site this morning and lifted the floor up and installed all of the steel beams.
The window and door frames have also been delivered ready to be installed. Updated photos below.
Steel around Alfresco Area
Side - Garage not in yet
Front
Kitchen Area
Lounge
Entry
Windows/Doors