Friday 27th March 2015
Our front doors have been installed meaning we are finally locked out! We've had to resort to peering through windows or hope to catch a tradie at site.
It was a quiet start to the week but today the stairs were stained and underlay installed - carpet tomorrow!
Friday, March 27, 2015
Thursday, March 19, 2015
Plumbing Fit Off Including Taps
Friday 20th March 2015
Things have slowed down a fair bit with only the plumbing fit off completed this week.
Our correct front door has arrived at last!
Things have slowed down a fair bit with only the plumbing fit off completed this week.
Our correct front door has arrived at last!
Tuesday, March 10, 2015
Saturday, March 7, 2015
Thursday, March 5, 2015
Terrace Balustrading
Thursday 5th March
Terrace balustrade has been installed. Feels a lot safer when we go out on the terrace now!!!
Terrace balustrade has been installed. Feels a lot safer when we go out on the terrace now!!!
Monday, March 2, 2015
Laundry Bench, Render Completed & Shower Screen Frames
Monday 2nd March 2015
The stone bench contractor has installed the laundry bench and increased the hole for the galley sink.
Tuesday 3rd March
The render to the front of the house has been completed as well as the terrace wall.
Wednesday 4th March
Stegbar have been in and installed the frame to both shower screens.
The stone bench contractor has installed the laundry bench and increased the hole for the galley sink.
Tuesday 3rd March
The render to the front of the house has been completed as well as the terrace wall.
Wednesday 4th March
Stegbar have been in and installed the frame to both shower screens.