We Are Locked Out!!

Friday 27th March 2015

Our front doors have been installed meaning we are finally locked out!  We've had to resort to peering through windows or hope to catch a tradie at site.





It was a quiet start to the week but today the stairs were stained and underlay installed - carpet tomorrow!
























Thursday, March 19, 2015

Plumbing Fit Off Including Taps

Friday 20th March 2015

Things have slowed down a fair bit with only the plumbing fit off completed this week.
 










Our correct front door has arrived at last!


Tuesday, March 10, 2015

Saturday, March 7, 2015

Garage Roller Door

Saturday 7th March

The garage roller door was installed today.  Outside is almost complete!






Thursday, March 5, 2015

Terrace Balustrading

Thursday 5th March

Terrace balustrade has been installed.  Feels a lot safer when we go out on the terrace now!!!





Monday, March 2, 2015

Laundry Bench, Render Completed & Shower Screen Frames

Monday 2nd March 2015

The stone bench contractor has installed the laundry bench and increased the hole for the galley sink.

 





Tuesday 3rd March

The render to the front of the house has been completed as well as the terrace wall.










Wednesday 4th March

Stegbar have been in and installed the frame to both shower screens.