Monday 26th January
We were away for the Australia Day long weekend but the builders worked! We dropped by Monday evening to find the roof frame up.
Saturday, January 24, 2015
Friday, January 23, 2015
Painting Finished
Friday 23rd January
Checked out the progress before dinner and were surprised to find that the painting was competed. Final coats on walls, doors, skirts, frames, etc. Really happy with the color choice and finish.
Checked out the progress before dinner and were surprised to find that the painting was competed. Final coats on walls, doors, skirts, frames, etc. Really happy with the color choice and finish.
Wednesday, January 21, 2015
Scaffold Removed
Wednesday 21st January
The scaffold around the perimeter of the house has been removed. Guys were working past 7pm to pull it down.
Painting has continued inside - looks like they have completed the gloss paint
The scaffold around the perimeter of the house has been removed. Guys were working past 7pm to pull it down.
Painting has continued inside - looks like they have completed the gloss paint
Monday, January 19, 2015
Painting Continues
Monday 19th January
The place is looking great, with the beginning of the painting process starting today.
Saturday, January 17, 2015
Painting Started
Saturday 17th January
Looks like the painters have started. Gap sealer put on and some cutting in started.
Blue-board has been installed to to the back balcony and cement sheet flooring to both balconies.
Looks like the painters have started. Gap sealer put on and some cutting in started.
Blue-board has been installed to to the back balcony and cement sheet flooring to both balconies.
Tuesday, January 13, 2015
Eaves, Floor Sand & Plaster
Wednesday 14th January
Seems like PD are back into it! Checked on the site today and found that the eaves have been installed, floors sanded upstairs and some final plasterwork is being completed around the stairs and wardrobes.
Met with a landscaper today about the retaining walls needed down the side and the back of the block - just waiting on his price. We are looking to use the concrete patterned sleepers. The retaining wall at the back corner of the block will be nearly 2m tall!!
We have also sent an application to South East Water to get our tap and water meter relocated. At present it is in the middle of our driveway.
Seems like PD are back into it! Checked on the site today and found that the eaves have been installed, floors sanded upstairs and some final plasterwork is being completed around the stairs and wardrobes.
Met with a landscaper today about the retaining walls needed down the side and the back of the block - just waiting on his price. We are looking to use the concrete patterned sleepers. The retaining wall at the back corner of the block will be nearly 2m tall!!
We have also sent an application to South East Water to get our tap and water meter relocated. At present it is in the middle of our driveway.
Friday, January 9, 2015
Facade & Brick Clean
Friday 9th January 2015
We haven't been to the block for few weeks as we have been away for the Christmas Holidays but a few things have been done.
The render to the facade looks like it is complete (except for the final color) and the bricks have been cleaned.
We haven't been to the block for few weeks as we have been away for the Christmas Holidays but a few things have been done.
The render to the facade looks like it is complete (except for the final color) and the bricks have been cleaned.