Wednesday 3rd December

Busy day at site - bricks continued down the back and side of the house, electrical and plumbing rough in and the insulation batts were delivered. 







Posted by Allison and Adam at Wednesday, December 03, 2014
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest

No comments:

Post a Comment

Newer Post Older Post Home
Subscribe to: Post Comments (Atom)

Blog Archive

  • ►  2015 (48)
    • ►  October (1)
    • ►  September (2)
    • ►  July (2)
    • ►  June (3)
    • ►  May (6)
    • ►  April (4)
    • ►  March (6)
    • ►  February (14)
    • ►  January (10)
  • ▼  2014 (46)
    • ▼  December (17)
      • Kitchen, Cabinets, Doors, Skirting & Architraves
      • Bricks Day 19, 20 & 21
      • Stairs!
      • Bricks Day 17 & 18
      • Bricks Day 16
      • Bricks Day 15
      • Bricks Day 14 + Cornice
      • Bricks Day 13 + Plaster Finished
      • Plaster!
      • Scaffold Errected
      • Bricks Day 11 + Window Installation and Scaffold D...
      • Bricks Day 10 - Gararge and Wall Insulation
      • Bulkhead
      • Bricks Day 8 & 9 + Electrical Rough In and Plaster...
      • Bricks Day 7 + Electrical, Plumbing, Air Condition...
      • Bricks Day 6 + Air Conditioning and Ducted Vacuum ...
      • Bricks Day 5
    • ►  November (16)
    • ►  October (6)
    • ►  September (1)
    • ►  August (1)
    • ►  February (4)
    • ►  January (1)
  • ►  2013 (1)
    • ►  December (1)

Visitors

Picture Window theme. Powered by Blogger.