Friday, April 10, 2015

Bits 'n' Pieces

Friday 10th April 2015


With only a few weeks to go there have been lots of smaller jobs completed this week including;

* Laundry door fitted
* Garage door fitted
* Ceiling to entry completed
* PD Site Supervisor paint defects (blue tape)
* Paint touch ups/completion internal and external
* Carpet to downstairs rooms (spare and study)
* Fly screens
* Builders clean (not an Allison clean!)
* Window clean
* Tiling/grout completion
* Skirting to lounge (after wall straightening)
* Site clean
* Inspection for CofO
* PD Quality Inspection










We haven't taken possession yet but we have started some work in preparation;
* Water meter and tap relocation from middle of driveway to side fence
* Screen fence constructed as required by council for overlooking




Next week we have our inspection with hand over the week after.... hopefully!!




No comments:

Post a Comment